Site Activity
Phase I – Early Site Work
Phase 1 began on August 5, 2009, and took approximately 11 weeks to complete. The site work entailed the following activities:
-
Property line cleared and perimeter fence installed
-
Interior site cleared and grubbed; erosion control installed
-
Sewer line for off-site connection drilled; receiving pit for utility lines constructed; water line relocated; and existing foundation debris from previous residences disposed
-
Sanitary sewer line for off-site connection drilled
-
Site graded and hydro seeded
Phase 1 work was completed in November 2009.
Phase II – Construction
Phase 2 is scheduled to take approximately 22 months. Lydig Construction, Inc. was awarded the construction contract
in the amount of $53,998,902.27 (including Washington State sales tax). The Notice of Award was issued November 30, 2009.
The following activities are anticipated to take place within the next few months:
-
Under slab utilities and footings
-
Wall panel erection
-
Structural steel roof installation
-
Installation of individual cells
-
Interior and exterior finishings
Photographs
Construction - July 2010
Construction - June 2010
Construction - May 2010
Construction - April 2010
Construction - March 2010
Construction - February 2010
Construction - January 2010
Construction - October to December 2009
Ground Breaking Ceremony Photos - August 10, 2009