Site Activity

 

Phase I – Early Site Work

Phase 1 began on August 5, 2009, and took approximately 11 weeks to complete. The site work entailed the following activities:

  • Property line cleared and perimeter fence installed
  • Interior site cleared and grubbed; erosion control installed
  • Sewer line for off-site connection drilled; receiving pit for utility lines constructed; water line relocated; and existing foundation debris from previous residences disposed
  • Sanitary sewer line for off-site connection drilled
  • Site graded and hydro seeded

Phase 1 work was completed in November 2009.



 

Phase II – Construction

Phase 2 is scheduled to take approximately 22 months. Lydig Construction, Inc. was awarded the construction contract in the amount of $53,998,902.27 (including Washington State sales tax). The Notice of Award was issued November 30, 2009.

The following activities are anticipated to take place within the next few months:

  • Under slab utilities and footings
  • Wall panel erection
  • Structural steel roof installation
  • Installation of individual cells
  • Interior and exterior finishings



 

Photographs


Construction - July 2010

Construction - June 2010

Construction - May 2010

Construction - April 2010

Construction - March 2010

Construction - February 2010

Construction - January 2010

Construction - October to December 2009

Ground Breaking Ceremony Photos - August 10, 2009

 
Copyright © 2010 South Correctional Entity Public Development Authority
For Questions, please contact Penny Bartley at scorejail@rentonwa.gov.
All rights reserved