Timeline


2009

January Cities take legislative action to establish SCORE
Schematic Design is completed for the facility
February - March The SCORE Public Development Authority established
Facility design development begins
Site in Des Moines selected
April Formal application for building permits
Facility design development completed
May - June Construction documents
July Construction bidding for site work
August - September Early site work begins
Construction bidding for general contractor
October Construction bonds issued
November Early site work completed
Contract awarded
December Construction begins



2010 Preliminary Schedule

January Foundation footings; under slab utility work
February - May Wall panel erection; utility installation
June Steel superstructure for roof
July Interior electrical
August Interior and exterior painting
September Sidewalks; exterior site lighting
October Mezzanine; stairs and rails
November Exterior landscaping
December Interior case work



2011 Preliminary Schedule

January Finish electrical and security hardware
February Finish plumbing and security glass
March Finish carpentry, casework and fire sprinklers
April Flooring installation
May Paint; security hardware; finish mechanical
June Paint; security hardware
July Substantial completion; furniture installation
August Punch list
September Final completion
 