Timeline
2009
|
January
|
Cities take legislative action to establish SCORE
Schematic Design is completed for the facility
|
|
February - March
|
The SCORE Public Development Authority established
Facility design development begins
Site in Des Moines selected
|
|
April
|
Formal application for building permits
Facility design development completed
|
|
May - June
|
Construction documents
|
|
July
|
Construction bidding for site work
|
|
August - September
|
Early site work begins
Construction bidding for general contractor
|
|
October
|
Construction bonds issued
|
|
November
|
Early site work completed
Contract awarded
|
|
December
|
Construction begins
|
2010 Preliminary Schedule
|
January
|
Foundation footings; under slab utility work
|
|
February - May
|
Wall panel erection; utility installation
|
|
June
|
Steel superstructure for roof
|
|
July
|
Interior electrical
|
|
August
|
Interior and exterior painting
|
|
September
|
Sidewalks; exterior site lighting
|
|
October
|
Mezzanine; stairs and rails
|
|
November
|
Exterior landscaping
|
|
December
|
Interior case work
|
2011 Preliminary Schedule
|
January
|
Finish electrical and security hardware
|
|
February
|
Finish plumbing and security glass
|
|
March
|
Finish carpentry, casework and fire sprinklers
|
|
April
|
Flooring installation
|
|
May
|
Paint; security hardware; finish mechanical
|
|
June
|
Paint; security hardware
|
|
July
|
Substantial completion; furniture installation
|
|
August
|
Punch list
|
|
September
|
Final completion
|